HomeMy WebLinkAboutThe Goderich Signal-Star, 1987-11-25, Page 26Valleys & People - Fail 1987 -- Page 2
Listowel Conduit Reconstruction Continues
The Listowel Flood Control project con-
tinues to make good progess. Construction
of the 8th Phase of the project will be com-
pleted in November.
With the completion of Phase 8, which
includes the short section of conduit up-
stream of Wallace Avenue North, only one
year of work remains to complete the en-
tire flood control project.
Construction of Phase 8 began early m
August. This phase involved the recon-
struction of the conduit inlet at the Wallace
Avenue North bridge and the retaining
wall along the east side of the Maitland
River. Good weather and low water levels
on the Maitland River has allowed work to
move ahead quickly. Construction is ex-
pected to be complete about one week
ahead of schedule.
Rideau Valley Constructors Ltd. of
Stratford was selected as the builder of
Phase 8. This contractor was chosen from
five tenders submitted at a tender price of
$355,150.
Eighty-five per cent of the cost is funded
by the Ontario Government through the
Maitland Valley Conservation Authority.
The remaining 15 per cent will be paid by
the Town of Listowel, as the benefitting
municipality.
It was anticipated that Phase 7 of the
project, involving the reconstruction of the
conduit on the south side of Main Street
would proceed in 1987. However delays
were experienced in finalizing landowner
agreements. Phase 7 is expected to be
undertaken in 1988.
Work on PhaSe 6, on the north side of
Main Street, was completed last Febru-
ary. Two of the three buildings demolished
to make way for Phase 6 have been rebuilt
with a third to follow.
Completion of all eight phases of the pro-
ject will reduce the chance of flooding in
downtown Listowel to one in 100 each year
from the previous level of one in seven.
The flooding problem in Listowel was
aggravated by the old conduit that chan-
nels river water through and under the
town. The small size and poor construction
of the old structure caused flood waters to
backup, overtopthe conduit and flow into
the streets. The new conduit has a much
greater capacity to carry flood waters.
The rebuilding of the conduit has been
discussed since the 1950s. In 1975 the
MVCA prepared a report at the request of
the Town of Listowel evaluating various
flood control proposals. A plan to upgrade
Goderich Bluffs project
completed for 1987
The second phase of construction of a
breakwall along the Goderich waterfront
was completed in March of this year.
The breakwall, or groyne, was built
adjacent to the town's pollution control
plant to protect beach area from the
punishing waves of Lake Huron. This is the
first step in the long-term goal of controll-
ing erosion of the bluff itself.
The work completed this spring included
a 61 metre rock extension to the first sec-
tion of breakwall built in 1986.
About 1,600 tonnes of armour stone was
placed on the site by Owen King Construc-
tion Ltd. of Walkerton, contractors for the
project. The total cost of the 1987 work was
$107,000. Eighty-five per cent of the cost
was paid by the Ontario Government
through the Maitland Valley Conservation
Authority. The Town of Goderich, as the
benefitting municipality paid the remain-
ing 15 per cent .
the conduit was agreed upon.
Since that time the project has seen the
replacement of two highway bridges,
channel improvements in the south end of
Listowel and reconstruction of all but the
last remaining section of conduit on the
south side of Main Street.
PHASE 8—Demolition of the old conduit upstream of the Wallace Avenue North
bridge took place earlier this year to make way for Phase 8 of the conduit recon-
struction.
Although this project is designed pri-
marily to protect property on the water-
front, the breakwall has created new
recreation potential on the Goderich shore.
A new stretch of sand beach has formed
behind the breakwall and is being enjoyed
by area residents and visitors.
The problem of erosion along the
Goderich waterfront has long been recog-
nized. Both the pollution control plant and
a number of residences will eventually be
threatened by the erosion of the bluff.
The bluff is eroding back from the shore
at a rate of about one metre per year.
The Maitland Valley Conservation
Authority is continuing to pursue govern-
ment fundingfor the engineering and re-
pairs to the bluff itself. A lack of funding to
Conservation Authorities prevented this
work from proceeding in 1987. The MVCA
will continue to pursue funds in 1988.
GOING UP—New buildings are being constructed on Main Street in Listowel.
These structures replace those demolished prior to the reconstruction of Phase
6 of the conduit rebuilding project.
WATERFRONT–The view from the top of the Goderich Bluffs shows the
breakwall to protect the shoreline from Lake Huron waves.
NEEDING REPAIR—Future work on the Goderich Waterfront will include the re-
pair of the badly eroded bluff.