Loading...
HomeMy WebLinkAboutLakeshore Advance, 2013-11-20, Page 15r Stantec to engineer STF design t T Wednesday, November 20, 2013 • Lakeshore Advance` 15 d CONTINUED FROM > PAGE 1 An RFP is not necessarily awarded based on the low hid. The bids cache in Stan- tec Consulting- $1,395,000, BM Ross $1,859,993 and Genivar $1,299,840. 'technical staff from each municipality had the oppor- tunity to review the submis- sions and confirm that all were submitted per the REP requirements and signed/sealed correctly. The estimated cost of the contract at thy time of the RIP release was $1,860,000. The Board was pleased the hid came in under the estimated cost. Brent Klttrner, l,ainbton Shores Director of (:ommu pity Services told the Lake- shore Advance, "The RFP documents do not indicate the provision of contingency pricing as this is not the typi- cal practice at this stage. Costs of the design project will be closely monitored by staff. Contingency allowances will be considered at the time of awarding the actual construc- tion of the facility. The munic- ipality typically applies con- tingency during the construction tender." Lampton Shores repre- sentative deputy mayor Eliz- abeth Davis 1)agg wanted the with the engineering and construction numbers broken down. Kittmer explained that as stipulated in the RFP documents, and protected under contract law, only the lump sum of the contract is made public, and propriety information affecting the competitive- ness of each bidder remains confidential. At the end of the Board meeting Davis Dagg asked to go in camera to ask for the breakdown. South Moron clerk Michael I)ILullo said they went in camera under Sec- tion 239(2)(a) and there was no rise and report after the in -camera as it was " simply information only" BACKGROUND OF THE PROJECT In 2005-06 the "Grand Bend and Area Sewage Serv- icing Master Plan" was car- ried out jointly by the Munic- ipality of Lambton Shores, Municipality of Bluewater and Municipality of South I luron, The first considera- tion in the Master Plan was to assess the need for an updated and expanded Sew- age 'Treatment Facility currently servicing the former village of Grand Rend (now Lan)bton Shores) and the surrounding area in the former Stephen 'Township (now South Huron). The Master Plan was followed up in 2008-09 with the "Grand Bend Sewage Treatment Facility Expansion & upgrade Environmental Study Report and Preliminary Design Report': The design of the Sewage Treatment Facility was final- ized in 21)10 to serve the entire service area and to meet a 2031 population pro- jection for a total average daily flow of 4,659tn3/d and a maximum month flow of 7,867m3/d. 'Through the Municipal (;lass Environ- mental Assessment process an Orbal' system oxidation ditch was selected as the pre- ferred treatment alternative to sleet the needs of the three municipalities. Fund- ing in the amount of approx- imately $15.9 million ($14.9 million two thirds Canada Build Canada Funding, $1 trillion Green Municipal Funding (;rant and $10 mil- lion low interest loan) has been secured for this project and is required to be expended prior to March 31, 2016 Upon the completion Of detailed design, the Engi- neer's estimate was higher than the project costs used for the funding applications. In October 2011 the project was tendered with two options, full build or a single treatment train. The lowest tender price for hill build was $23.2 trillion and $ 18.(1 million for single train. Con- sidering all of the project costs and other factors, the three partner Municipalities decided not to proceed. 'the tender award period was allowed to lapse and no con- tact was awarded. Subsequent to the expiry of the tenders, Lampton Shores and South Huron (the joint owners of the exiting sewage lagoon) expressed a desire to move forward with a modified project to expand and upgrade the existing facility. Accordingly, the Grand Bend Area Sewage Board appointed a Working Group to evaluate lower cost wastewater treatment alter- natives that would meet the current needs of the com- munity for a 20- year design horizon; was expandable to accommodate future needs; and could he constructed within the grant eligible lim- its. The current system on Mollard lime in South Huron consists of four facultative lagoons in series with a design capacity of 1,891 m3/d and is approaching its cur- rent rated capacity (actual flows plus committed capac- ity). 1.amhto11 Shores and South Huron are joint own- ers in this facility. 'Ihe Working Group evalu- ated various alternatives based on a projected phase one Clow of a total average daily flow of 2,473m3/day and presented their finds to the Grand Bend Area Sewage Board. The Board selected the option of the Orbal'sys- tem with more extensive flow equalization and value engi- neering, essentially this is a scaled down version of the original design, maximizing the use of the existing lagoon cells for flow equalization. An addendum to the origi- nal Sewage Treatment l ity ESR was carried out in 2012. At the conclusion of the public consultation proc- ess a number of Part 11 Order request were received. The MOE denied the Part 11 Order requests on September 11, 2013. A scope change appli- cation was made to the Funding Agencies based 00 a phased plant and including the modifications to the main sanitary pumping sta- tion in Grand Bend, On August 1:3 201:3 Building Canada approved the scope change request and the Municipalities of Latnhton Shores and South Huron now wish to move forward witlh the project. PURPOSE '1'o re -design an already completed design of the full !mild -out Grand Bend Area Wastewater Treatment Facil- ity and include upgrades to the existing Main Pumping Station (PS -2) as identified in the ESR addendum filed in October 2012, Update/obtain the necessary approvals and revise the existing tender documents so that this project can be re -tendered and construction completed prior to funding deadline of March :31, 2016. This will involve a review of the exist- ing Wastewater Treatment Facility design; re -design as necessary to facilitate a phased approach that can accommodate future expan- sion and utilize the existing lagoon cells to maximize flow equalization. PROJECT COSTS The total cost of the project will he one of the criteria in the consultant selection process and is the upset limit for the project. It is antici- pated that the total cost to re -design, revise the tender documents and obtain approvals for the Grand Bend Arya Sewage Treat- ment Facility and PS -2 upgrades is approximately six hundred thousand dol- lars ($600,000). It is antici- pated that the total cost to re -tender the project, pro- vide construction inspection and project administration services is approximately one million and forty thou- sand dollars ($1,040,000) (Le. 8% of the estimated con- struction cost of $13M). The anticipated cost to provide engineering services associ- ated with the PS -Upgrades, including tendering, con- struction inspection and project administration serv- ices is approximately two hundred and twenty thou- sand dollars ($220,000) (i.e. 15% of the estimated con- struction cost of $1.45M). The total cost of the project will be one of the criteria in the consultant selection proc- ess and is the upset limit for the project. It is anticipated that the total cost to re -design, revise the tender documents and obtain approvals for the Grand Bend Area Sewage Treatment Facility and PS -2 upgrades is approximately one 01illion eight hundred and sixty thousand dollars ($1,860,000), TIIA'I' Report I)(:S 150 - 2013 50- 201:3 regarding the 'RI:P Award - Engineering Design Arbortech/Taylor Professional "Tree (',ire Inc. Visit us at www. arbortechtree.ca to see what we can do for you! 519-238-5451 VISA OD Est. 1994 -,fory*.p,..wevt.wAvermeorwt,.. 1979 lagoons on Mollard Line and Construction Adminis- tration Services for the Grand Bend Area Sewage Treat- ment Facility upgrade' be received; and TIIAT Council accept the recommendation from the Joint Board, and award the proposal for engineering design and construction administration services for the Grand Bend Area Sewage Lynda Hillman-Raplay OMI Agnecy Treatment Facility upgrade project submitted by Stantec Consulting be awarded at the bid price of $1,395,000; and 1'I IAT Council direct staff to negotiate a services con- tract with Stantec Consulting using the standard Munici- pal Engineers' Association services contract, to be returned to a future Council sleeting for acceptance. Sarnia -Lampton Economic Partnership COMMUNITY INVITATION Public Meeting Join us as we update our Strategic Plan 2012-2015. Thursday, November 28, 2013 7:30 am — 9:00 a.m. Location: 1loliday Inn Sarnia/Pt. Edward, 1498 Venetian Boulevard, Sarnia Keynote speaker Ian Maclellan will discuss news about Ubiquity Solar Inc and their plans to develop a manu- facturing facility for polysilicon production. Polysili- coI1 IS used 111 computer chips, and Photovoltaic ('ells. There is no cost to attend, however you must reserve your seat by November 20th by calling Jeanny Leung at 519-332-1820, or by email rcccption(a Sarnialamh- ton.on.ea or by visiting the Sarnia-1.amhton Economic Partnership website, events page (www.sarnialanlbton. on.ca). SARNLA LAM BT Economic Partnership